The countdown begins

This is what a site office looks like when it’s waiting for the works to begin.  It’s been a long time coming, but work is about to get underway!

It’s been a few months since I wrote about the trials and tribulations of finding a builder.  Getting building consent approved for a change of use was starting to seem like a walk in the park!  I’d been using word-of-mouth referrals to find good local tradies, but hadn’t been able to find someone willing and available to take on the job.

Fortunately my well-networked neighbour came to the rescue with the name of a friend who had recently started their own building business after moving back from Auckland.  We arranged to meet on-site in early July, and he was keen to take on the job.  Unfortunately he wasn’t available to start until early September, but I figured that would give me enough time to get rid of the mountain of boxes I hadn’t sorted through before my move.

Unfortunately the start was delayed until December, which gave me heaps of time to sort out the things you need to have in place for a major works contract:

  1. Construction contract – recommended for all building works, and mandatory for anything over $30,000 including GST.  Fortunately the government’s building website has a link to a free contract you can download and use.
  2. Insurance – if you have domestic building insurance then you may need to get additional cover for the construction works.  My kirk is classified as a commercial building, so my insurance policy covered $100,000 worth of construction work.

However, trying to get an insurance certificate via my insurance broker was a drama that took nearly three weeks to resolve.  You have to provide your contractors with a copy of your insurance certificate as part of your contract with them.

In the process of getting my insurance certificate, I discovered that the insurer wasn’t going to extend my cover beyond 28 February 2020.  They had seen it as a short-term arrangement, and despite taking over $6,000 from me in 18 months, they didn’t want the continued risk of an un-occupied commercial business.

The pressure was now on to get the conversion completed to a stage that would enable me to get domestic building insurance cover in place by the end of February.  I would need to make sure that my builder had everything on site when he needed it in time to meet this deadline.

I already had the cabinets onsite as well as the tap-ware.  He’d order the timber he needed so it was just the shower and toilet I’d need to sort.  My original choices were no longer available, so I did the expedient thing and chose standard items from the local builder’s merchant catalogue.

I already had a bench-top oven, electric jug, and coffee plunger on site, but decided to add a fridge and toaster to the site ‘kitchen’.  I’ve also dug out my old microwave just in case.  Note the old-fashioned bowl on the bench-top oven for washing up – but not at the same time.  Now all we need is to get water connected to the building!

22 - Site kitchen

Next time:  Driving with the whole body

Leave a comment